Configuring Risk-Based Testing

To configure Risk-Based Testing, perform the following steps:

QPro_TC_RBT_Settings.png
  1. Go to Project Management and click Projects.

  2. Open the General Settings tab.

  3. Move to the Risk Analysis section.

If Enabled

  • The system displays Risk Analysis fields for unarchived test cases, requirements, Data Parameterized test cases, and Exploratory test cases.

  • Copying entities in the same project also copies their values.

  • Copying entities to a different project transfers values only if RBT is turned on.

  • For Projects with Jira Integration, the following fields are displayed on the Test Case detail page in Jira:

    • Risk Type

    • Risk Category

    • Likelihood

    • Impact

    • Risk Priority Number (RPN)

    • Extent of Testing

If Disabled

  • The values are hidden but preserved. Re-enabling will restore the Risk Analysis values.