Mapping and Unmapping Single Jira Project

Map a single Jira project to a QMetry project so that the selected Jira work items sync to the QMetry Requirements module, the Issues module, or both.

Map a Single Jira Project

To map a Jira project, perform the following steps:

  1. Go to Project Management and open Projects.

  2. Select the project and go to Jira Integrations.

  3. Select the Jira URL to map with QMetry project.

    QPro_JI_JiraProjMapping.png
  4. Select the Jira project to configure.

  5. Set the Jira Work Items and QMetry Module associations.

    Note

    • Work Item is a multi-select list.

    • For mapping requirements, select a folder.

  6. Apply JQL filters to customise Jira work items syncing with QMetry Requirements and Issues.

  7. Click Save and Activate.

Note

To save a project mapping, map at least one work item to the Requirements module or the Issues module.

Unmapping previously configured work items

When you remove work items that are mapped to a module, QMetry updates the related data as follows:

  • When you remove one or more work item type mappings from the Requirements module, QMetry converts the existing synced work items into internal requirements.

  • When you remove one or more work item type mappings from the Issues module, QMetry deletes the existing synced work items along with all their associations.

Projects Without Work Item - Issue Module Mapping

When a QMetry project is integrated with an external tracker but no work items are mapped to the Issues module, , the following behavior applies:

  • QMetry disables issue creation and linking options across Requirements, Test Cases, Executions, and Exploratory Testing.

  • The Issues module does not display any issue list or filter options. Instead, it displays a message that no work items are mapped.

  • Issue-based dashboards and issue sections in system reports appear blank.